Dependencies


The Dependencies tab enables you to specify the work project's dependencies, if any. You can create tasks as a planning tool but not link them to a service request or work order, or you can associate a task with a work order or service request. If you create a new work order or service request and link it to the task, the start and due dates are those of the task. Tasks may be dependent on other tasks in the same project.

Detail View Header

The field in the top section of this tab defines the data that displays.

Work project ID

Identifier of the work project currently selected in the grid or that you are inserting (opening). The application assigns the ID; this field is display only.

Detail View

Data in the fields on the bottom section of this tab provide details about the work project's dependencies. Unless otherwise indicated, these fields are required.

Delete

If this field has a check, the entire row is deleted when you click Save.

Line number

Line number. Defaults to 0. Maximum field length is five characters.

Line description

Displays the description of the line from the Project Lines tab for more information while working with lines. This field is display only.

Depends on line number

Line number on which the project depends. Must be 1 or higher, and must exist in the project. Maximum field length is five characters.

Depends on line description

Displays the description of the line for which this line depends on, from the Project Lines tab, for more information while working with lines. This field is display only.

Lead days

Number of days between the date the dependent task ends and this task begins. May be positive or negative number (to allow for lags). Maximum field length is five characters. Optional.

Synchronize dates

If this field has a check, the dates are synchronized. Defaults to unchecked (no synchronization).